Winter break will be a busy time on the second floor (east side) of FHG library. With the help of a generous donor, the area to the left of the help desk will be revitalized into an engaging student space. During that time, the space will be unavailable for studying or computer use. Activity will begin on Monday December 15 with the removal of computers. See the timeline below for more details.
Timeline
Date
Activity
December 15
Computers Removed
December 16 - 18
Space Cleared and Demo
December 19 - January 12
Construction
January 13
Space Cleaned
Week of January 26
Furniture Installation
Floor Plan, Furniture, and Finishes
This post has no comments.
Commenting on blog posts requires an account.
Login is required to interact with this comment. Please and try again.
FHG Space RefreshWinter break will be a busy time on the second floor (east side) of FHG library. With the help of a generous donor, the area to the left of the help desk will be revitalized into an engaging student space. During that time, the space will be unavailable for studying or computer use. Activity will begin on Monday December 15 with the removal of computers. See the timeline below for more details.
TimelineDate
Activity
December 15
Computers Removed
December 16 - 18
Space Cleared and Demo
December 19 - January 12
Construction
January 13
Space Cleaned
Week of January 26
Furniture Installation
Floor Plan, Furniture, and FinishesCommenting on blog posts requires an account.
Login is required to interact with this comment. Please and try again.
If you do not have an account, Register Now.